Welcome

This website is now an archive of the restoration and should only be used as a resource. Please visit the Lion Salt Works website for the most up-to-date information.



Welcome to the Lion Salt Works blog

The Lion Salt Works is a historic brine salt making site that is being restored and transformed into a unique heritage attraction. Led by Cheshire West and Chester Council, this £8million project will see the site reborn as a fascinating destination for tourists, day visitors and families and a valued resource for local communities, businesses and heritage interest groups.

Located in the village of Marston, close to the town of Northwich, the site lies adjacent to the Trent and Mersey Canal and is close to the historic Anderton Boat Lift. A substantial part of the site is a Scheduled Monument.

Restoration work has now started on the site, with an expected opening in spring 2015. The Lion Salt Works is currently closed to the public.

Thursday, 15 May 2014

May 2014 Update: Lifts, Stove Houses, Pans and Bridges


The new disabled lift access is fitted to the Red Lion Inn
The lift shaft and emergency exit to the Red Lion Inn
The roofs of the Historic Core

Looking North over the Adelaide Flash with the restored Historic Core in the foreground


The Stove House 2 floor has begun to be repaired

Internal repairs of the Stove House 2 floor


A set of workman's clogs were discovered below the floorboards


The last of the repairs on the exterior of Stove House 2

Stove House 5 across the remains of Pan 2

Pan 5 has sat on a temporary scaffold for the last 5 years, ready to be lifted back into place
Pan 5 is lifted into place
Pan 5 sits on several steel girders

Pan 5 in position


The new path layout is established to the entrance of Stove House 5

The entrance to Stove House 5 is now in place

The Link Bridge, between Stove House 5 and the Historic Core is beginning to be built

The Loading Bay repairs have begun

The last of the repairs on the Pump House chimney have been completed

Wednesday, 16 April 2014

April 2014 Update: A Tour through the Museum

The  museum experience is beginning to take shape. For the first time the route the visitor takes through the Lion Salt Works can be seen. 

The entrance foyer in Stove House 5
Cloak rooms and toilets to the rear
A cafe with views to Pan 5 outside
From Stove House 5 the visitor walks down via Stove House 4 and Pan House 4 to the Red Lion Inn

The visitor will be able to visit the museum displays in the Red Lion Inn...
From the Red Lion Inn, the visitor passes into Pan House 3
Lift and stairs give access to all
Pan 3, surrounded by a balustrade
The walkway passes over the flues
...or passes north into Stove House 3
The walkway gives a circular route around the stove houses
...with stairs into the warehouses

From the warehouse of Stove House 3, the visitor passes into Stove House 4

Museum displays will be present in Stove House 4...
...with views of the crushing machine

To be continued......

Wednesday, 5 March 2014

March 2014 - A Winter of Transformation



A winter of hard work and the buildings and site are beginning to be transformed...
 Stove House 5

The scaffold has been removed from the exterior of Stove House 5
Stove House 5 is visible from Stove House 2


The new emergency walkway and details of the steel girder supports replicating those around the original building

Dawn through the windows of Stove House 5
The ground floor foyer of Stove House 5 takes shape
A lick of paint
The original beams recovered from Stove House 5 have been reused in the upstairs conference facility
The Historic Core - South



The entrance to Pan House 3 is revealed for the first time
The roofs are on the buildings in the historic core
The curving side of Stove House 4 carefully rebuilt is revealed when the scaffold is removed
The new stairways and walkways have been built to allow pedestrian access to the historic core

The new stairway onto the hurdles in Pan House 3

New metal railings have been put around Pan 3
The railings continue across the flues at the end of Pan 3

The scaffold has been removed from Stove House 4 Warehouse and the protected crusher revealed, the floor has been relayed
Historic Core - North

The buildings in the Historic Core North are beginning to come together

The Loading Bay area is cleared
New steel feet are added to the existing posts
The architect, structural engineer and site managers discuss repairs to the lanterns on Stove House 2 roof

Stove House 2 roof is complete
The eastern face of Stove House 2 above Pan 2 has been repaired
The scaffold has been removed from the interior of Stove House 2
The Red Lion Inn



The exterior repairs around the Red Lion Inn are complete
Work begins on the interior alteration to the Red Lion Inn to convert it to the museum
 External Works

During the excavation for the utilities remains of the fishery pans have been revealed and carefully excavated by Oxford Archaeology North

The train tracks of the mineral railway have been revealed connecting the pan houses to the main Cheshire Lines. These will be preserved beneath the roadway